3. CONTENTS
Description Quantity
Softener body 1 unit
100 - 240 VAC voltage transformer 1 unit
2.5” wrench for the head flange 1 pc.
3/4” connector 2 pcs
3/4” seal 2 pcs
Worm drive hose clip 1 pc.
Non-collapsible hose 1 running metre
4. PREPARATION FOR INSTALLATION
After unpacking of the device, a power supply, a 2.5”
wrench for the head flange, 3/4” seals and 3/4” con-
nectors shall be taken out of the brine tank. Only the
special recesses in the housing shall be used to lift
and move the device around. The device shall not be
lifted by its electric cables or water hoses due to da-
mage that might occur.
Before installing, ensure that water mains pressure
is above 1.5 bar and below 6.0 bar. Shall the pressu-
re be higher, a reducing valve shall be installed
upstream the device.
A location as close as possible to the water inlet of a
building shall be chosen (a water meter in case of
mains water supply or a hydrophore in case of own
water source/inlet) and in the vicinity of drainage.
Moreover, permanent electric power supply is ne-
cessary, therefore a socket must be near. The surfa-
ce of installation must be stable and must withstand
the weight of the device filled with water. Ambient
temperature in the selected installation area shall
never drop below 5°C, otherwise the device may be
permanently damaged. The devices shall not be in-
stalled in rooms with excessive air humidity. What is
more, the selected area shall be large enough to gu-
arantee free access to the device, as it requires pe-
riodical refilling of salt.
5. INSTALLATION
The connectors of the control head are marked as IN (inlet)
and OUT (outlet), looking from the front of the control head: IN
(inlet) on the right, OUT (outlet) on the left. The seals and con-
nectors provided shall be placed/fixed onto the connectors of
the control head. The water softener shall be connected to the
system with flexible hoses (not provided). A mechanical filter
shall be installed upstream the softener, of at least 50 mi-
crons, in order to protect the device against impurities.
A by-pass can be executed by means of regular valves, as indi-
cated in Fig. B. A turbine must be installed in a nipple fixed
onto the “OUT” connector of the control head. Before installa-
tion, make sure that the turbine rotates freely (e.g., by blowing
air into the water outlet). The device shall be installed by me-
ans of materials intended for water installations. In case of any
problems or doubts, contact a qualified installation company