If more Local burner/boiler systems exist in the network than
can reasonably fit on the page, Previous page and Next page
buttons (see Fig. 45) are used to move between the burner/
boiler systems on the page. These buttons appear only when
the total number of burner/boiler systems exceeds the display
limit.
Fig. 45. System S7999D scrolling.
FUEL AIR RATIO CONTROL
COMMISSIONING
Commissioning Process
Commissioning the R7999 using the S7999D System Display
requires the following general steps:
1. Connecting the R7999 to the S7999D and logging into
the system with a password. (This is the commissioning
password for the R7999 controller. The factory default is
"password" (without the quote symbols)). This prevents
unauthorized users from modifying the modulation curve.
2. Specifying the base configuration: one or two fuels, with
or without FGR.
3. Selecting system parameters such as Low Fire Hold.
4. Specifying the characteristics of the actuators and
setting the valve/damper endpoints for those actuators.
5. Creating a modulation curve (profile) for each fuel and
verifying it from maximum to minimum modulation.
(While you are commissioning the system, you must
monitor the burner operation with appropriate safety
instrumentation to verify the modulation curve.)
Commissioning Overview
The following table provides a step-by-step overview of how a
system is commissioned.
The Notes column in the table provide references to detailed
information when completing the more complex operations.
.
Table 3. S7999D Home Page Status Variables
Burner/boiler system
component Status variable
Burner Control Sequence state
Burner Control Fault code
Burner Control Flame Signal Strength
R7999 Fuel selection
R7999 Fault code
R7999 Firing rate
Stack Temperature controller Current temperature
Stack Temperature controller High/Low temperature alarm
Stack Temperature controller FGR permissive alarm
PID Load controller Current water temperature
PID Load controller Current steam pressure
PID Load controller Low Fire Hold alarm
Feed Pump Level controller Current vessel level
Feed Pump Level controller High water alarm
Steam/Fuel Flow Monitor Current steam flow
Steam/Fuel Flow Monitor Current gas flow
Steam/Fuel Flow Monitor Current fuel oil flow
Thermal Shock controller Current water supply
temperature
Thermal Shock controller Optimal temperature alarm
Table 4. Commissioning Overview.
Step Action Notes
1 On the Home page screen, press R7999 device icon.
2 On the Fuel/Air Ratio Control screen, select Commission, then
press "Do Commissioning" button.
3.a. Enter R7999 Commission password. The S7999D requires you to enter the R7999
Commission password. The factory default password
is “password”.
3.b. Set new password for new R7999 (factory state).
4 On the Commission Configuration screen, perform the following
steps: