7
Installation Preparations
The charger power is within the allowed load range of the residence.
Cables and RCBOs meet the installation and usage requirements.
If the AC input power cable exposed to the outdoor environment is 3 m or longer, consult the local installer. You are advised
least 3 m.
A network cable that is long enough is prepared if the charger is connected to a wired network.
The installation area should be covered by a wireless network if the charger is connected to the network through WiFi.
QR code in "About This Manual" and see detailed information about the meter in "Meter Description."
Before the installation, ensure that:
Preparing Tools
Personal protective
equipment
Safety helmet
Hardware installation
tools
Hammer drill and
Protective gloves Insulated shoes
Phillips insulated torque
screwdriver (M4/M5/M6)
Insulated security torx
torque screwdriver (TT20)
Rubber mallet
Marker
Cable installation tools
Wire stripper
Crimping tool Scissors
Measurement instruments
Clamp meter
Steel measuring tape Level instrument
Auxiliary materials
Insulation tape
Heat-shrink tubing Cord end terminal
Preparing an RCBO
Note: To facilitate cabling, aluminum wires and solid copper wires are not recommended.
Specifications
Input
Single-phase /
Three-phase
2P/4P RCBO, 40 A (50 A is recommended if the ambient temperature is higher than 45°C), Type A
or B, in compliance with local regulations.
Preparing Cables
Operating Current
Cable Type
AC input power cable (single-phase three-wire)
32 A
Cross-sectional Area
6~10 mm
2
6~10 mm
2