3.4 Installing a PE Cable Between the ICC Cabinet and the
Isolation Transformer
Procedure
Step 1 Prepare a cable of suitable length and install OT terminals on both ends of the cable.
Step 2 Connect the PE cable to the ground bar.
Ensure that the ground cable is installed securely. Inappropriate grounding may cause device
damage and personal injury.
Figure 3-7 Installing a PE cable for a single ICC cabinet
(1) Site ground bar