Meter
Model
Power
Lowering
Adjustment
Period
Maximum
Protection Time
Description
UMP209 0.5s 3s
CHNT
DTSU666-H
0.5s 3s Under the Spanish
RD1699 grid standard,
please set Power
Lowering Adjustment
Period 0.8s, Maximum
Protection Time 2s
The preceding parameters are tested in a lab environment and can be
preferentially used for
conguration and commissioning onsite. They may need to
be adjusted based on the actual situation.
SmartLogger3000
Export Limitation Conguration Guide 3 Conguting Export Limitation Feature
Issue 04 (2022-10-24) Copyright © Huawei Technologies Co., Ltd. 19