v SPCN card (see symbolic FRU “TWRCARD” on page 470) in the failing unit (first frame with a
failure indication)
v SPCN card (see symbolic FRU “TWRCARD” on page 470) in the preceding unit in the string
v SPCN optical adapter A in the preceding unit in the string
v SPCN optical adapter B in the failing unit
v SPCN optical cables C between the preceding unit in the string and the failing unit
(A) SPCN
Optical .----- (C) SPCN
Adapter ----. | Optical Cables
| |
| | .-- (B) SPCN
.---------. | | | Optical
| System | | | | Adapter
| Unit | V | V
| J15 | .-. V .-.
’----.----’ | +------------+ |
| | +------------+ |
.----’----. .-------’-+ .-------’-+ .---------.
|Sec J15 | | Sec J16| |Sec J15| | Sec |
|Unit J16+-+J15 Unit | |Unit J16+-+J15 Unit |
| 1 | | 2 | | 3 | | 4 |
’---------’ ’---------’ ’---------’ ’---------’
^
|
|
’--- Failing Unit
This ends the procedure.
24. Does the SPCN frame-to-frame cable coming from the system unit connect to J15 on the secondary
unit (where the power on light is off or the unit control panel displays a power reference code of 1xxx
xxxx)?
v No: Correct the connection by connecting the SPCN frame-to-frame cable coming from the system
unit to J15 of the secondary unit.
This ends the procedure.
v Yes: Continue with the next step.
25. Perform the following:
a. Power off the system.
b. Disconnect the SPCN frame-to-frame cable from J15 connector of the first unit that cannot
become powered on.
c. Connect the negative lead of a multimeter to the system frame ground.
d. Connect the positive lead of the multimeter to pin 2 of the SPCN cable.
Note: Use an insulated probe or jumper when performing the voltage readings.
e. Note the voltage reading on pin 2.
f. Move the positive lead of the multimeter to pin 3 of the SPCN cable.
g. Note the voltage reading on pin 3.
Figure 8. SPCN cable connector. (RV2A180-1)
Is the voltage on both pin 2 and pin 3 from 1.5 V dc to 5.5 V dc?
v Yes: Exchange the following FRUs, one at a time (see Remove and replace procedures).
– SPCN card (see symbolic FRU “TWRCARD” on page 470) in the failing unit.
– SPCN card (see symbolic FRU “TWRCARD” on page 470) in the preceding unit in the unit
string.
– SPCN frame-to-frame cable.
This ends the procedure.
60 iSeries: iSeries Server 270, 800, 810, 820, 825, 830, 840, 870, 890, SB2, and SB3 Hardware Problem Analysis and Isolation