NOTES.
Ensure all boss blanking plugs are removed before connecting hardware. Each valve must be tted to the correct boss as shown
in the picture.
Ensure each union is tted with bre seals provided.
Do not subject any of the isolating valves to heat as the seals may be damaged.
WATER CONNECTIONS CH
1. Connect the CH ow service valve provided in the
hardware pack to the threaded boss connection
provided at the lower rear of the boiler.
2. Connect the CH return valve (black handle).
3. If connecting the boiler to heating loads in excess of
60,000 Btu/h (17.5kW), connecting ow and return
heating systems pipework must be sized in 28mm
diameter at the point of pipe connection to the
boiler tails. Use 22mm x 28mm pipe adaptors as
appropriate.
GAS CONNECTION
IMPORTANT. The gas service cock is sealed with a non-
metallic blue bre washer, which must not be overheated when
making capillary connections. Refer to Frame 1 for details of the
position of the gas connection.
For additional gas supply information refer to “Gas Supply” on
page 8.
SAFETY VALVE DRAIN
The safety valve connection, located at the bottom right-hand
side of the boiler, comprises a 15mm diameter stub pipe.
N.B. Use a compression tting when connecting to the safety
valve drain pipe to facilitate replacement of the safety valve if
required.
The discharge pipe should be positioned so that the discharge
of water or steam cannot create a hazard to the occupants of
the premises or damage the electrical components and wiring.
WATER CONNECTIONS DHW
1. Fit the DHW inlet service valve (blue handle) to the
threaded boss connection ensuring the seal provided is
correctly located.
2. Fit the DHW outlet pipe tail to DHW outlet connection,
ensuring the seal provided is correctly located.
23
CONNECTIONS & FILLING
FILLING
IMPORTANT -whenlling:
A. Ensure the dust cap on air vent
located at the rear of the pump
chamber is slightly unscrewed.
B. When lling, there may be a slight
water leak from the air vent therefore
electrical connections should be
protected.
CH -
1. Ensure that the CH isolating
handles are open.
2. Fill and vent the system. Refer to
Frame 2 for setting pressure.
DHW -
1. Fully open all DHW taps and ensure
that water ows freely from the.
2. Close all taps.
Dust Cap
Note.
The DHW ow rate is automatically regulated to a max:
24 = 9.9 l/m (2.2 gpm)
30 = 12.4 l/m (2.8 gpm)
Note that all isolation
handles are shown in the
open postion.