PREPARATION FOR INSTALLATION
2-11
2.6 Work Flow for AIS Installations for Ships in Commission
Work Item
Responsible
Section
Note
Acceptance of Order Marine Sales
Department/Agent
Schedule confirmation
1) Confirmation of work time
2)
Confirmation of ship inspection
3)
Preparation of documents requested by a ship owner and
confirmation of submission time
Marine Sales
Department / TMS
Department
Ship inspection (confirmation using a checklist) TMS Department /
Agent
Preparation of work drawings (Expansion of drawings by ship
inspection)
1)
System diagram
2)
Drawing for antenna installation position (Based on the
existing antenna layout drawing and ship inspection
information)
3)
Drawing for antenna fixing pole
4)
Drawing for device installation
Front wall in the bridge
Radar indicator
Chart table, etc.
5)
Drawing for cable path (including fixing locations of cable
glands)
TMS Department /
Engineering
Department
Preparation of work plan
1) Work date. (Decide a work period based on workload.)
If the work cannot be completed once (some part of the work
is saved for another day due to navigation), planning is done
to separate the installation of the equipment from the
preparatory work. (However, it is difficult to separate the work
in consideration of the supplementary work.)
2) Location of work
3) Responsible person for the work (including an agent)
4) Work application (work procedure)
Supplementary work
Removal of ceilings
Removal of walls
Working on walls for device installation, etc.
Hot work
Fixing an antenna pole
Mounting a cable gland
Fixing brackets for a device table
Fixing devices
Cabling
Cabling
Binding: Use of existing cable paths
Recovery from the supplementary work
Recovery of ceilings
Recovery of walls, etc.
Connection (Makers are responsible for external devices.)
Gyrocompass
GPS receiver
Speed log
Others
Functional test (based on the test manual)
TMS Department /
Agent
TMS
Department
will check
the plans
prepared by
agents.
Preparation of the work report and test report. TMS Department /