4.2 Operation
4.2.1 Commissioning unfilled batteries
Z The operations required must be carried out by the manufacturer's customer
service department or a customer service organisation authorised by the
manufacturer.
4.2.2 Commissioning filled and charged batteries
Checks and operations to be performed before starting daily work
Procedure
Make sure the battery is in physically good condition.
Make sure the terminals are correct (positive to positive and negative to negative)
and check that contacts on the battery terminal conducting system are secure.
Check the M10 terminal screws of the conductors and connectors are secure and
if necessary torque to 23 ±1 Nm.
Charge the battery, see page 13.
Check the electrolyte level of each battery cell after charging and top up if
necessary:
Open the plug (15).
Z The electrolyte level should not be less than the "Min" electrolyte marking (16)
and must not exceed the "Max" (17) marking.
If necessary, add electrolyte with pure water up to the "Max" electrolyte level
marking (17), see page 15.
Close the plug (15).
The test is now complete.
Battery cell cross section Top view of a battery cell