2.2. SITING THE MACHINE
When siting the machine, the following have to be considered:
Site the machine on a fixed dry base, which does not cause dust etc. into the suction air of
cooling.
Make sure that the machine is placed away from the line of particle spray from grinding
tools.
Ensure free circulation of the cooling air. Make sure that there is at least a 20 cm free dis-
tance both in front of and at the rear of the machine for the circulation of the cooling air.
Protect the machine against heavy rain and in hot circumstances against direct sunshine.
2.3. START OF INSTALLATION
Mastertig AC/DC 2500 and -2500W: Check first that the
mains voltage change-over switch is in right position.
If it is necessary to change mains cable, do it before moun-
ting to the wheel barrow T 120. Otherwise you possibly
have to dismount the machine.
Before connecting the machine to the mains supply, one
of the three panels, the ACDC panel, the ACDC minilog
or the ACDC pulse panel, has to be installed. Installation
instructions 4283280 are in the package of the panel.