Installation and Service Guide N5251-90001 3-9
PNA Series Microwave Network Analyzer System
N5251A
System Installation
PNA, Control
ler, and
Test Head Module Interconnections
PNA, Controller,
and Test Head Module Interconnections
Mount PNA on Top of Controller
Mount the PNA on top of the N5261/2A controller as shown in Figure 3-1 on page 3-10 and
Figure 3-2 on page 3-11. Use the Lock Link kit (U3021-60003) to mechanically connect the two
units. Detailed instructions are contained in the “System Configuration and Operation” section
of the N5261A and N5262A User’s and Service Guide (N5262-90001).
Rear Panel Cabling
Figure 3-1 on page 3-10 and Figure 3-2 on page 3-11 illustrate the rear panel cabling for 2-port
and 4-port systems. Torque all RF connections to 10 in-lbs (1.13 N.m) to insure proper
connection.