Chapter 4: Smoke control acceptance and testing 
62  VM-1 Smoke Management Application Guide 
Periodic testing 
During the life of the building, maintenance is essential 
to ensure that the smoke control system will perform its 
intended function under fire conditions. Proper 
maintenance of the system should, as a minimum, 
include the periodic testing of all smoke control 
equipment including VM-1 SCS controls, initiating 
devices, fans, dampers, controls, doors, and windows. 
The equipment should be maintained in accordance with 
the manufacturer’s recommendations. Refer to  
NFPA 90A, Standard for the Installation of Air 
Conditioning and Ventilating Systems, for suggested 
maintenance practices for nondedicated HVAC and 
damper requirements. NFPA 92A, NFPA 92B, and 
NFPA 72 should be consulted for smoke control panel 
testing. 
These tests should be performed on a periodic basis to 
determine that the installed system continues to operate 
in accordance with the approved design. 
The smoke control system should be tested in 
accordance with the following schedule by persons who 
are thoroughly knowledgeable in the operation, testing, 
and maintenance of the systems. The results of the tests 
should be documented in the operations and 
maintenance log and made available for inspection upon 
request. 
Dedicated Systems 
Weekly: Automatic testing every seven days of 
dedicated systems will operate all components. 
Automatic tests must be recorded, with failure of any 
monitored components noted. 
Semiannually: Operate the smoke control system for 
each control sequence in the original design and 
observe the operation of the correct outputs for each 
given input. Tests should be conducted under standby 
power, if applicable. 
Nondedicated Systems 
Annually: Operate the smoke control system for each 
control sequence in the approved configuration and 
observe the operation of the correct output for each 
given input. Tests should be conducted under standby 
power, if applicable. 
Special arrangements might have to be made for the 
introduction of large quantities of outside air into 
occupied areas or computer centers when outside 
temperature and humidity conditions are extreme. Since 
smoke control systems override limit controls, such as 
freezestats, tests should be conducted when outside air 
conditions will not cause damage to equipment and 
systems.