90 TP-6694 2/25
For KG25, KG30, and KG40A (KG02L04T Engine), use the following:
See Figure 37.
Natural Gas Operation
Disconnect FSN from FS.
Connect 70NG1 and NGN to FV1.
Connect 70NG2 and NG to FV3.
LPG Vapor Operation
Connect FSN to FS.
Connect 70LP1 and LPN to FV2.
Connect 70LP2 and LP to FV4.
Figure 37 Gaseous Fuel Connections Wiring Diagram, KG25-KG40A (KG02L04T)
KG25, KG30, and KG40A (KG02L04T Engine) Dual Fuel Connections
Automatic changeover dual fuel systems are factory connected. No changes to the electrical connections for a dual fuel system
are required in the field. The connections are shown in the connection diagrams for reference.
Figure 38 Gaseous Fuel Connections Wiring Diagram, KG25-KG40A (KG02L04T)
ADV-10009
ADV-10009
Auto Changeover Natural Gas and LPG Vapor