3. Install the Bath
Leveling
Blocks
Rim
Cement or
Mortar Bed
CAUTION: Risk of personal injury. Do not lift the bath by the rim. Lift the
bath from the boom only.
Cement or Mortar Bed Method
NOTICE: Do not use gypsum cement or drywall compound for this application, as
they will not provide an acceptable, durable bond.
If desired, lay a plastic lm on wood suboors to prevent water absorption.
Spread a 1" (25 mm) to 2" (51 mm) layer of cement or mortar on the suboor.
With help, lift the bath into position.
Verify that the bath is level. Reposition or shim as needed.
Construction Adhesive Method
Apply a generous amount of construction adhesive to the boom of the support
blocks or molded supports.
With help, lift the bath into position.
Verify that the bath is level and resting on all supports. Reposition or shim as
needed.