AIR HANDLING UNIT FUTURE
INSTRUCTIONS FOR OPERATION AND MAINTENANCE
Humidifying secon, steam FKTH
32 V. 2.0 2017-02-13
11. HUMIDIFYING SECTION, STEAM FKTH
11.1. Installation
The steam humidifying section is installed on the Future inspection section FTTT, according to the humidifier
manufacturer’s instructions.
11.2. Commissioning
Check the condensation water discharge system, i.e., drip tray, piping and water trap. Flush the piping and fill
the water trap.
CAUTION
Commission the humidifier, according to the manufacturer’s instructions.
11.3. Maintenance
Check and clean the condensation water discharge system, i.e., drip tray, piping and water trap.
CAUTION
Service the humidifier, according to the manufacturer’s instructions.