12
[7] Vaporizer Connections
• Vaporizer Connections (WG972-GL· WG752-GL only)
The hose length between the vaporizer and carburetor must be within 300 ±20 mm (11.8 ±0.78 inch).
3. Production Installation Checklist
• The emissions-related installation design (intake & exhaust system, gasoline fuel temperature test, etc.)
is verified during the Application Review. The Application Review must be completed before the
equipment is released to the market.
• Below is a checklist to be used during the final assembly of each production unit.
Incorporate this checklist into your manufacturing process.
Emissions-Related Installation Check List Page Yes No
1
Correct intake system confirmed at application review and/or the Exhaust Emission
Check Sheet installed?
2-3
2 Correct catalyst (Kubota parts) is installed? 4
3 Catalyst identification information is kept with the engine information? 5
4 Correct exhaust system installed? 6
5 Torque of catalyst parts installation is correct? 7
6 Correct spacer and related parts are installed? (If necessary) 8
7 Is the other parts layout around the catalyst parts correct? 8
8 Correct fuel system (fuel tank~purge port) confirmed at application review installed? 9-10
9 Range of engine operation speed is correct? 10
10 EPA and CARB emissions labels are visible? 11
11 The hose length between vaporizer and carburetor is correct? 12