5
[4] Regulator Connections
Regulator Connections
The hose length between the regulator and gas mixer must be within 300 ±20 mm (11.8 ±0.78 inch).
3. Production Installation Checklist
NOTE
The emissions-related installation design (intake system, natural gas fuel system, and etc.) is verified
during the Application Review. The Application Review must be completed before the equipment is
released to the market.
Below is a checklist to be used during the final assembly of each production unit.
Incorporate this checklist into your manufacturing process.
Emissions-Related Installation Check List Page Yes No
1
Correct intake system confirmed at application review and/or the Exhaust Emission
Check Sheet installed?
1-2
2 Range of engine operation speed is correct? 3
3 EPA emission label is visible? 4
4 The hose length between the regulator and gas mixer is correct? 5