Starting up
13.04.99
YACE0059
19
6.5.2 Low-level protection and testing
"
""
"

Double signal tone sounds, if the bath liquid falls so
much that the heater is no longer covered with liquid
completely
1. The display shows LLL (low-level) and the fault triangle
is flashing
!
heating is switched off on both poles,
!
pump and refrigeration system are switched off by
the electronics.
2. Top up the bath
Section 5.2 and reset with the key.
If necessary repeat several times in case that the pump does not purge
immediately.
Testing at regular intervals by lowering the bath level. Place a hose on the pump
connector and pump some of the bath liquid into a suitable container.
Step 1 - 2 must follow.
Bath temperature during this test not below 0°C or higher than 50°C, otherwise
danger of burn injuries !
If there is any irregularity when testing the safety devices, switch off the unit
immediately and pull out the mains plug !
Have the unit checked by the LAUDA service or the local service organisation!
6.5.3 Pump motor monitoring
In case of pump motor overload or a blockage the heating and the pump are
switched off.
"
""
"

Double signal tone sounds.
The display shows PPP for pump and the fault triangle
is flashing
Rectify the cause of the fault, e.g. clean the pump or
check the viscosity, then
reset with the key.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lauda RE 112 and is the answer not in the manual?

Lauda RE 112 Specifications

General IconGeneral
BrandLauda
ModelRE 112
CategoryThermostat
LanguageEnglish

Related product manuals