Launch TLT235TLT240 Economical Two-post User’s Manual
17
B 520mm
(20.5
in)
235mm
(9.3in)
1#
C
线
3
4
1
0
m
m
(
1
3
4
.
3
i
n
)
φ
22mm(0.9in)
4
3
2#
A
2610mm(102.8in)
2770mm(109.1in)
3370mm(132.7in)
235mm
(9.3in)
380mm
(15in)
25mm(1in)
Fig.9c
TLT235SC(U) asymmetric installation is shown in Fig.10a
TLT235SCTLT240SC asymmetric installation is shown in
Fig.10b
z With total width (A) as the basis, draw two parallel
lines (#1 and #2) on the concrete slab, with the error
within 3mm.
z
Determine a point B at any point on chalk line #1,
based on point B, move down 131mm, then move
right 228mm to get point C. Based on point B, draw
#1’s vertical line M with a length of A to get point
D .Based on point C, draw line M’s parallel line N with
a length of L to get point E. With four points B,C,D,E,
each post’s position can be decided.
E
D
C
B
2#
A
1#
131mm(5.16in)
228mm
(8.98in)
228mm
(8.98in)
3544mm(139.53in)
3088mm(121.57in)
Fig.10a
Diagonal 3410mm (134.3in)