Installation Manual 45
ENGLISH
Test Run
Test Run
1
2
3
4
5
Check to see whether there is any refrigerant leakage, and slack of power or transmission cable.
Confirm that 500 V megger shows 2.0 (1.0) MΩ or more between power supply terminal block and
ground. Do not operate in the case of 2.0 (1.0) MΩ or less.
NOTE: Never carry out megaohm check over terminal control board. Otherwise the control board
would be broken.
Immediately after mounting the unit or after leaving it turned off for an extended length of time,
the resistance of the insulation between the power supply terminal board and the ground may
decrease to approx. 2 (1) MΩ as a result of refrigerant accumulating in the internal compressor.
If the insulation resistance is less than 2 (1) MΩ, turning on the main power supply and energiz-
ing the crankcase heater for more than 12 hours will cause the refrigerant to evaporate,
increasing the insulation resistance.
Check if both gas and liquid valves are fully opened.
NOTE: Be sure to tighten caps.
Turn on universal power supply at least 12 hours before the test run to ensure the crank case heater
should heat up the compressor. If the turn-on hours of the heater are too short, it may result in a mal-
function of compressor.
Check if there are any problems in automatic addressing or not:
Check and confirm that there are no error messages in the display of indoor units or remote controllers
and LED in outdoor units.
Checks Before Test Run
Content of parentheses ( ) is for CRUN458S0