363-205-401 DT Turn Up: NTP-003
Issue 7, March 1997 Page 3 of 4
DO ITEMS BELOW IN ORDER LISTED FOR DETAILS, GO TO
4. Connect power to DT
A. At AC outlet box, insert 900A1 DT power plug into AC outlet.
DLP-500B. At pedestal DC power interface, connect 900A2 or 900A3
DT power cord and customer DC power feed pair if not
already done.
5.
NOTE:
Do not connect J104 to the batteries at this time.
Install 900A1, 900A2, or 900A3 DT batteries in tray in bottom of
DT closure.
DLP-5016. Install
ASH1 PCU
.
DLP-5027. If required, install
EAF1
drop test module on
ASJ2
channel unit.
DLP-5038. Install
ASJ1
or
ASJ2
channel unit and secure.
9.
NOTE:
If electrical connector J105 is not connected to P105 on the
AYB1B
optical unit backplane, make the connection at this
time. When making the connection verify that the top of the
J105 connector (labeled
TOP
) is oriented properly.
DLP-504Install
AYB1B
optical unit.
DLP-50510. Power up DT.
DLP-50611. Measure voltages at
ASH1 PCU
faceplate.
12. Close and lock the AC outlet box. (900A1 DT only)
13. Close and lock the 900A1, 900A2, or 900A3 DT closure unless
end-to-end tests are to be performed at this time. Close pedestal
or DT enclosure if necessary.
14. Update office records.