FX20 INSTALL GUIDE
32 VERSION 1.6 | APRIL 26, 2024
CHANGE LOG
1.6
● Note: In this guide, "x-axis" means right-to-left, "y-axis" means front-to-back (with respect to
the printer).
● Added FX20 Accessory Kit/Bag and Required Partner Tools Checklist (pg. 6-7)
● Updated Level the Printer Chassis (pg. 12)
● Updated Level the Print Bed (pg. 17)
● Updated Set the Encoder Gaps (pg. 19)
● Added Device Setup Utility section (pg. 24)
● Added Chamber Temperature Calibration Utility section (pg. 26)
● Added Gantry Squaring Procedure (pg. 29)
1.5
Like the 1.3 revision, this update substantially reorders several sections of the install procedure and adds an
important additional step (the sign-o sheet on the next page). Please reread the Guide before proceeding
with your next install.
● Reorder sections/steps of leveling procedure
● Expected install time is now minimum two days on site
● Add belt tension check/adjustment before printing
● Add installer sign-o sheet including required measurements/photos
● Added digital calipers requirement to Additional Equipment list
● Minor clarications and rewording throughout
1.4
● Add gantry skew alignment before nozzle oset procedure
● Material loading and chamber heating are now handled by nozzle oset utility
● Add sample Day 1 schedule