Massey Ferguson 6400 - Issue 4.a
2A30.11
Splitting the front frame/Sisu engine - MF 6497-6499
Final operations
Final operations are not especially difficult. They there-
fore will be carried out in the reverse order of the
preliminary operations.
However, the following operations need to be
performed during refitting:
- if necessary, tighten the screws or wheel nuts at the
required tightening torque (see chapter 6);
- make up the level of coolant, to the maximum level
marked on the expansion tank (Fig. 16);
- test:
- the air conditioning system (if fitted - see
chapter 12);
- the suspended front axle (if fitted, see chapter 8),
- all mechanical, hydraulic, electrical and electronic
functions concerned by servicing;
- check the tightness:
- of the hydraulic unions,
- of water hoses,
- of the bleed screw on control unit of suspended
front axle (if fitted).
M
A
X
M
I
N
MA-02-05124A
Fig. 16