6. Folding Inspection
Please check the product before installation. Make sure nothing in the packaging is damaged
or missing. You should receive the following items in the package:
No.
Picture
Category
Quantities
1
Ultra Slim LiFePO4 Battery
1
2
Users Manual (Please keep it for future
reference)
1
3
Mounting Plate
2
4
Expansion Screw
6
5
Parallel power cable of battery (L=1500mm)
Connecting two batteries in order to connect
two or more batteries in parallel
Optional
Accessories
6
Paralle communication line RJ45(L=1500m)
Communication cable between batteries,
keeping two or more batteries
Optional
Accessories
7. Preparation before Inspection
Before choosing an installation location, consider the following:
7.1 Do not install this product on surfaces of flammable building materials.
7.2 Mounted on the surface of a solid material.
7.3 Please install this energy storage battery at eye level for a more intuitive view of the the LCD.
7.4 For heat dissipation, ensure that the distance is 20cm from both sides and 50cm from the
bottom of the u7nit.
7.5 The ambient temperature of the installation location should be between 0~45 degrees
Celsius to ensure optimal operation.
7.6 The recommended installation position should e vertically attached to the wall and kept at a
safe distance from other objects and surfaces to ensure sufficient space for heat dissipation
and wire collection.