4). Set the 2-way valve to the close position. 
5). Operate the air conditioner at the cooling 
cycle and stop it when the gauge indicates 
0.1Mpa(14.5Psi). 
6). Set the 3-way valve to the closed position 
immediately 
Do this quickly so that the gauge ends up 
indicating 0.3Mpa(43.5Psi) to 0.5 Mpa(72.5Psi). 
Disconnect the charge set, and tighten the 
2-way and 3-way valve’s stem nuts.   
Use a torque wrench to tighten the 3-way valves 
service port cap to a torque of 18N.m. 
Be sure to check for gas leakage. 
2. Air purging by the refrigerant 
 
Procedure: 
1). Confirm that both the 2-way and 3-way 
valves are set to the closed position. 
2). Connect the charge set and a charging 
cylinder to the service port of the 3-way valve 
Leave the valve on the charging cylinder closed. 
3). Air purging. 
Open the valves on the charging cylinder and 
the charge set. Purge the air by loosening the 
flare nut on the 2-way valve approximately 45’ 
for 3 seconds then closing it for 1 minute; repeat 
3 times. 
After purging the air, use a torque wrench to 
tighten the flare nut on the 2-way valve. 
4). Check the gas leakage 
Check the flare connections for gas leakage. 
5). Discharge the refrigerant. 
Close the valve on the charging cylinder and 
discharge the refrigerant by loosening the flare 
nut on the 2-way valve approximately 45’ until 
the gauge indicates 0.3Mpa(43.5Psi) to 0.5 
Mpa(72.5Psi). 
6). Disconnect the charge set and the charging 
cylinder, and set the 2-way and 3-way valves to 
the open position 
Be sure to use a hexagonal wrench to operate 
the valve stems. 
7). Mount the valve stems nuts and the service 
port cap 
Be sure to use a torque wrench to tighten the 
service port cap to a torque 18N.m. 
Be sure to check the gas leakage. 
6.7 Re-installation while the outdoor 
unit need to be repaired 
1. Evacuation for the whole system 
 
Procedure: 
1).  Confirm  that  both  the  2-way  and  3-way 
valves are set to the opened position. 
2). Connect the vacuum pump to 3-way valve’s 
service port. 
3). Evacuation for approximately one hour. 
Confirm that the compound meter indicates 
-0.1Mpa(14.5Psi). 
4). Close the valve (Low side) on the charge set, 
turn off the vacuum pump, and confirm that the 
gauge needle does not move (approximately 5 
minutes after turning off the vacuum pump). 
5). Disconnect the charge hose from the 
vacuum pump.