Service manual
- 16 -
8 Installation details
8.1 Wrench torque sheet for installation
Torque
mm inch Kg.m
φ6.35 1/4 1.8
φ9.52 3/8 4.2
φ12.7 1/2 5.5
φ15.88 5/8 6.6
φ19.05 3/4 6.6
Outside diameter
8.2 Connecting the cables
The power cord of connect should be selected according to the following specifications sheet.
Amp 10 15 20
2
1.0 1.5 2.5
Grade
8.3 Pipe length and the elevation
Standard
length
Max. Max. Additional
(m) Elevation Elevation refrigerant
1/2’’ (φ12.7) 1/4’’ (φ6.35) 5 5 10 30
5/8’’ (φ15.88) 3/8’’ (φ9.52) 5 10 20 65
Pipe size
7k~12K
16K~28K
30K~36K
Capacity
Caution:
Capacity is base on standard length and maximum allowance length is base of reliability.
Oil trap should be install per 5-7 meters.
In case
than 5m.