Chapter 5 Performance Checks
This chapter covers performance checks used to ensure that the ASTRO XTS 5000 radio meets
published specifications. The recommended test equipment listed in the previous section
approaches the accuracy of the manufacturing equipment, with a few exceptions. Accuracy of the
test equipment must be maintained in compliance with the manufacturer’s recommended calibration
schedule. Checks should be performed if radio performance degradation is suspected.
5.1 Test Equipment Setup
Supply voltage can be connected from the battery eliminator. The equipment required for the
performance checks is connected as shown in Figure 5-1.
Figure 5-1. Performance Checks Test Setup
BNC
NOT USED
AUDIO GENERATOR
SINAD METER
AC VOLTMETER
TX
RX
30 dB PAD
30 dB PAD
RF GENERATOR
SYSTEM ANALYZER
OR COUNTER
WATTMETER
MAEPF-27212-A
BATTERY
ELIMINATOR
REX-4424
TRANSMIT
RECEIVE
RADIO
PROGRAM/TEST CABLE
RKN4105 or RKN4106
AUDIO IN
SET TO APPROX. 450mV FOR Tx
MEASURE 80mV FOR Tx
SMA-BNC
58-80348B33
TEST SET
RLN-4460_