Commissioning/start-up
Switching on: Plug the power plug into the outlet.
The unit switches on immediately.
Lay the mains cable so that a drip loop is formed and the lowest point is below the socket. This
prevents dripping water from entering the socket.
Set the desired flow rate.
Switching off: Pull the power plug from the outlet.
Form a drip loop
Set the flow rate
BSE0003
BCT0014

Table of Contents

Other manuals for Oase BioCompact 25

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oase BioCompact 25 and is the answer not in the manual?

Oase BioCompact 25 Specifications

General IconGeneral
BrandOase
ModelBioCompact 25
CategoryWater Filtration Systems
LanguageEnglish

Related product manuals