36 
11.3 Outdoor Unit 
11.3.1  Install the Outdoor Unit 
  After selecting the best location, start installation according to Indoor/Outdoor Unit Installation Diagram. 
1  Fix the unit on concrete or rigid frame firmly and horizontally by bolt nut (ø10mm). 
2  When installing at roof, please consider strong wind and earthquake. 
Please fasten the installation stand firmly with bolt or nails. 
 
AB
C
D
 
 
Model A B C D 
C9***  474 mm 87 mm  18.5 mm 261 mm
C12***, C18***  570 mm 105 mm  18.5 mm 320 mm
C24***  613 mm 131 mm  16 mm 360.5 mm
11.3.2  Connect the Piping 
11.3.2.1 Connecting the piping to indoor 
Please make flare after inserting flare nut (locate at joint portion, of tube assembly) onto the copper pipe. (In case of 
using long piping) 
Connect the piping 
  Align the center of piping and sufficiently tighten the flare nut with fingers. 
  Further tighten the flare nut with torque wrench in specified torque as stated in the table. 
11.3.2.2 Connecting the piping to outdoor 
Decide piping length and then cut by using pipe cutter. Remove burrs from cut edge. 
Make flare after inserting the flare nut (locate at valve) onto the copper pipe. 
Align center of piping to valves and then tighten with torque wrench to the specified torque as stated in the table. 
 
To r q u e
wrench
Spanner
or Wrench
 
 
 
 
 
 
 
 
Do not overtighten, overtightening may cause gas leakage 
 
 
Piping size  Torque 
6.35 mm (1/4”)  [18 N•m (1.8 kgf.m)] 
9.52 mm (3/8”)  [42 N•m (4.3 kgf.m)] 
12.70 mm (1/2”)  [55 N•m (5.6 kgf.m)] 
15.88 mm (5/8”)  [65 N•m (6.6 kgf.m)] 
19.05 mm (3/4”)  [100 N•m (10.2 kgf.m)]