3. HOW TO INSTALL THE INDOOR UNIT
3-1. Required Minimum Space for Installation and Maintenance Services
This air conditioner is usually installed above the ceiling or behind the wall so that the indoor
unit and ducts are not visible. Only the air intake and air outlet ports are visible from below.
The minimum space for installation and maintenance services is shown in the figure.
< Horizontal installation >
Unit: mm Unit: mm
B
A (Suspension bolt pitch)
B (Inspection access)
Inspection
access
450 × 450
(Field supply)
Inspection access
800 × B
(Field supply)
Min. 650
Ceiling
(Inspection access)
Floor
(200)
450
Min. 1,800
Min. 350
Min.
250
Min.
20
Min.
20
Min. 300
70
Minimum space for installation and
maintenance services
Unit: mm
Type
15, 22, 28,
36, 45, 56
60, 73, 90
106, 112, 140,
160
A (Length) 867 1,067 1,467
B (Length) 850 1,050 1,450
It is necessary to make space for the cleaning and
maintenance of the drain pan, the heat exchanger and filter
fixed inlet.
Do not put any obstacle not to cause obstructing
maintenance or cleaning works.
If the place where the ceiling material cannot be removed,
make an
inspection access (800 × B) below the bottom
surface of the indoor unit in order to take it out.
If no space to provide inspection access (800 × B), there are two alternative cases (1 or 2 as below). However, when choosing
those cases, there is not enough space available to offer heat exchanger maintenance service.
1
Make space more than 300 mm between the indoor unit’s
bottom surface and the ceiling material.
2 Install inspection access (450 × 450) both edge of indoor
unit and make space more than 100 mm between the indoor
unit’s bottom surface and the ceiling material.
(Inspection access)
450
Min.
300
450 450
(Inspection access) (Inspection access)
Min.
100
Unit: mm
Unit: mm
Unit: mm
Inspection access
450 × 450
(Field supply)
Inspection access
450 × 450
(Field supply)
(150) (200)
(Inspection access)
800