EN | User Manual Start-up
22 BSP-MT 10-95/D3
Start-up
Warning!
The dryer must be taken into operation by trained personnel only! Untrained
personnel does not have the required knowledge. Such personnel might cause
serious faults.
Note:
You can order the initial commissioning and start-up from the manufacturer
and have your personnel trained by the manufacturer. For telephone number,
see page 4.
◊ Carry out all prescribed tests and checks.
◊ Before start-up, ensure that no tools or other foreign parts have been left lying in a part of
the dryer where they might pose a hazard to the dryer being started up.
Requirements for initial start-up
For the rst start-up the following preconditions must have been met:
◊ The pipe system is free from contaminations.
◊ All shutdown valves are closed.
◊ The dryer is correctly sited and installed.
Checks before start-up
Ensure that
◊ all pipe, cable and bolt connections on the dryer have been retightened,
◊ no pipes chafe against body edges,
◊ all mountings are perfectly secure,
◊ the needle valve of the oil indicator is closed,
◊ the electrical connections are in safe contact and in good condition,
◊ owner-end and pressurised parts such as safety valves or other devices are not blocked up
by dirt or paint,
◊ all compressed air system parts which are pressurised (valves, hoses etc.) are free from
wear symptoms and defects.