6EM Thru 18GM - 1100 Vertical Turbine Pumps 41
12/99 Layne/Verti-Line
Column Removal
Flanged Column
A. Install eyebolts of sufficient size in the
column flange holes and lift the unit and
reposition the clamp below the next
column flange.
B. Use column and shaft clamps (or other
acceptable method) to safely support
and lift this assembly.
C. Unbolt column flange and lift column
enough to loosen the shaft coupling.
When all components are loose,
carefully lift this assembly from the pump
unit. With soft skid boards under the
column to protect the flange, slowly
lower the column and shaft assembly
onto the floor and move to a convenient
work area.
IMPORTANT
Shaft threads are left-hand rotation.
D. Repeat above steps A, B & C until all
column and shaft sections have been
removed from the unit.
E. Remove the bearing retainer assembly
for inspection and cleaning.
F. Remove shaft section from column pipe.
Remove couplings from shafts and
inspect for wear or damage.
G. Inspect bearings and retainers for
damage.
H. If the top and intermediate drive shaft
sleeves (13 & 29) show wear or damage
remove the sleeve by heating it to 350
°
F-
400
°
F to break the Loctite bond.
IMPORTANT
Measure and record the position of the
sleeves (13 & 29) on the shafts before
removal. They must be put back in
exactly the same place.
CAUTION
To prevent possible serious personal
Injury always wear heat resistant gloves
when handling heated parts.
I. Refer to Pump Bowl Disassembly for
detailed bowl disassembly procedures.
Threaded Column
A. Install eyebolts of sufficient size in the
column flange holes and lift the unit and
reposition the clamp below the next
column coupling.
B. Use column and shaft clamps (or other
acceptable method) to safely support
and lift this assembly.
C. Unscrew the column coupling and lift
column enough to loosen the shaft
coupling. When all components are
loose, carefully lift this assembly from
the pump unit. With soft skid boards
under the column to protect the threads,
slowly lower the column and shaft
assembly onto the floor and move to a
convenient work area.
IMPORTANT
Shaft threads are left-hand rotation.
D. Repeat above steps A, B, and C until all
column and shaft sections have been
removed from the unit.
E. Remove the bearing retainer assembly
for inspection and cleaning.
F Remove shaft section from column pipe.
Remove couplings from shafts and
inspect for wear or damage.
G. Inspect bearings and retainers for
damage.
H. If the top and intermediate drive shaft
sleeves (13 & 29) show wear or damage
remove the sleeve by heating it to 350°F-
400
°
F to break the Loctite bond.
I. Refer to Pump Bowl Disassembly for
detailed bowl disassembly procedures.