7 Commissioning
7.1 General
Danger
Commissioning may only be carried out by an approved installer.
The installer checks the tightness of pipes, the correct function of
all regulating, control and safety equipment, and measures the
combustion values. If this work is not carried out correctly, there is
a risk of considerable damage to persons, environment and
property.
7.2
Checklist for commissioning
Tab.13 Checklist for commissioning
1. System location
2. Customer
3. Boiler type/Designation
4. Serial number
5.
Characteristic gas val
ues
Wobbe index kWh/m³
6. Operating heating value kWh/m³
7. Have all pipelines and connections been checked for tightness?
8. Flue gas system checked?
9. Gas pipeline checked and vented?
10. Static pressure measured at the gas valve inlet? mbar
11. Free wheeling of pumps checked?
12. Filling the heating plant
13. Water additives used
14. Gas flow pressure measured at full load at the gas valve inlet? mbar
15. Gas injector pressure measured at full load at the gas valve outlet? mbar
16. CO
2
content at low load %
17. CO content at low load ppm
18. CO
2
content at full load %
19. CO content at full load ppm
20.
Function test:
Heating mode
21. Domestic water mode
22.
Programming:
Time /date
23. Comfort setpoint heating circuit 1/2 °C
24. Setpoint DHW °C
25. Automatic day time programme Clock
26. Heating curve checked?
27. Tightness of the flue system checked in operation (e.g. CO
2
test in annular gap)?
28. Customer instructed?
29. Documents handed over?
Only components tested and marked according to the respective standard have been used.
All system components have been installed according to the instruction of the manufacturers.
The whole system conforms to the standard.
To ensure the heat source operates reliably and economically for a long period, we recom
mend annual maintenance for the heat generator.
Date /signature
Company stamp
...............................