Testing operations
1. Check the power supply between the outdoor unit and the auxiliary circuit breaker.
1 phase power supply : L, N
3 phases power supply : R, S, T, N
2. Check the indoor unit.
1) Check that you have connected the power and communication cables correctly. (If the power cable and
communication cables one mixed up or connected incorrectly, the PCB will be damaged.)
2) Check the thermistor sensor, drain pump/hose, and display are connected correctly.
3. Press K1 or K2 on the outdoor unit PCB to run the test mode and stop.
K1 button is applicable for AF55JSMA model only
Press K1 button
Start Heating test mode
Press K1 button twice
Stop
Heating test mode 7-seg display :
Press K2 button Start Cooling test mode Press K2 button three times Stop Cooling test mode 7-seg display :
Press K1 button twice
Start Defrost test mode
Press K1 button
Stop
Defrost test mode 7-seg display :
• Condition of Defrost test mode
- Condition 1 : The outdoor temperature is under 10 °C
- Condition 2 : All the temperature conditions should meet the defrost conditions
Press K2 button twice
StartInverter Checkermode
Press K2 button twice
Stop
Inverter Checkermode 7-seg display :
Press K2 three times
Start Pump down mode
Press K2 button
Stop
Pump down mode 7-seg display :
Outdoor unit
ON
1 2 3 4
ON
1 2 3 4
4. After 12 minutes of stationary condition check each indoor unit air treatment :
Cooling mode(indoor unit check)
Inlet air temp. - Outlet air temp. : From 10 °C to 12 °C
Heating mode(indoor unit check)
Outlet air temp. - Inlet air temp. : From 11 °C to 14 °C
In heating mode, the indoor fan motor can remain off to avoid cold air blown into conditioned space.
5. How to reset the power supply of the outdoor unit and deactivate the eco mode (standby mode) :
Outdoor unit type A, B : Press K3 button over 1 sec to reset the power supply of the outdoor unit and deactivate the eco
mode (standby mode).
ENGLISH-62
PAC MIRAGE Saudi_IBIM_EN_CS6_DB68-04872A-05.indd 62 2016-08-08 오전 11:38:41