Switch Control Setup
Priority3_OpenXfer—Load shedding is not allowed. Load transfer allowed through
an open transition only.
Priority4_XferShed—Load shedding is allowed. Only shed after transfers to other
circuits have been considered. Priority 4 is the highest priority of this category.
Priority5_XferShed—Load shedding is allowed. Only shed after transfers to other
circuits have been considered.
Priority6_XferShed—Load shedding is allowed. Only shed after transfers to other
circuits have been considered.
Priority7_XferShed—Load shedding is allowed. Only shed after transfers to other
circuits have been considered. Priority 7 is the lowest priority of this category and will
be transferred or shed before Priority 6, 5, 4, etc.
Priority8_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits. Priority 8 is the highest priority of this category.
Priority9_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority10_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority11_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority12_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority13_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority14_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority15_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority16_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority17_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority18_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority19_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority20_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority21_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority22_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority23_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority24_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits.
Priority25_Shed—Load shedding is allowed. Shed these loads before considering load
transfers to other circuits. Priority 25 is the lowest priority of this category and will be
shed before any others.
Return to Normal Time
This setting is the amount of time, in minutes, power must be restored to the faulted
line segment before the Return to Normal process will start. (Range: 1 to 254 minutes;
Default: 5)