Commissioning
95
3 Commissioning
Perform the following activities for initial comissioning:
l Set the date and time
l Connect the plug-in power supply (for printer functions).
1 Press and hold down the <ì> key.
2 Press the <on/off> key.
The
display test
appears briefly on the display.
The measuring instrument then switches automati-
cally to the setting of the baud rate.
3 Press the <run/enter> key repeatedly until the date
flashes on the display.
4 Set today’s date by pressing <
> <>.
5 Confirm with <run/enter>.
The date (month) flashes on the display.
6 Set the current month by pressing <
> <>.
7 Confirm with <run/enter>.
The year appears on the display.
8 Set the current year by pressing <
> <>.
9 Confirm with <run/enter>.
The hour field flashes on the display.
10 Set the current time by pressing <
> <>.
11 Confirm with <run/enter>.
The minutes field flashes on the display.
12 Set the current time by pressing <
> <>.
13 Confirm with <run/enter>. The measuring instrument
then switches to the measuring mode.
14 Switch off the instrument by pressing <on/off>.
Setting the date
and time