15-1
Equipment
Manual OP7, OP17
Release 04/99
Commissioning
The
commissioning guide which follows explains the dif
ferent steps that
have to be taken to commission the OP
. Figure 15-1 shows the most impor
-
tant steps for initial commissioning, recommissioning and normal operation
of the OP
.
Download configuration data to OP
COM1/2
Switch the OP to download mode
during the startup phase
(see chapter 15.2).
Switch on power supply of the OP
Initial Commissioning
No configuration/firmware
exists on the OP.
Recommissioning
The OP already contains a
configuration but you want to
change the configuration or
use a new one.
Normal Operation
The OP is operated with the
loaded configuration.
Start screen or standby message
OP
ProTool
Figure 15-1 Commissioning Flowchart
Diagrammatic
representation
15

Table of Contents

Related product manuals