Preventative visual inspection of the shipping crate, Remote Pump
Unit, and accessories must be performed before installation.
Physical or electrical problems due to handling and vibration may
occur during shipment.
1. If the packing crate shows signs of damage inspect the
SPS cabinet for damage. Check the entire outside of the
cabinet for damage which could cause internal
mechanical or electrical problems.
2. Check main disconnect switch, door and hinge
operation.
3. Check pump/motor hardware for tightness. Rotate
motor shaft by hand and check for smooth operation.
Check pump/motor coupler for proper alignment and
spacing. The coupler should have approximately 1/8"
clearance between coupler halves. If this clearance is
reduced or the pump and motor are not properly aligned
excessive noise and pump/motor wear will occur.
4. Check all electrical terminals and connections for
tightness.
1.Properly mount and attach all components as shown in
the dimensional drawings using the mounting feet/holes
and plumbing provided. The pressure relief manifold
should be plumbed back to the main fuel tank.
2.Connect all components to earth ground at ground
studs provided as shown on the electrical drawings.
Unit must be grounded for operator safety.
3. If equipped, install level and alarm indication
accessories as shown on dimensional drawing and
connect them to the Pump Unit as shown on the
electrical drawings.
4. If equipped, connect dry alarm contacts for customer
use per specifications on the electrical drawings.
5. Connect pump motor/control power to the Remote
Pump Unit per specifications on the electrical drawings.