SJ46AJ SJ51AJ SJ63AJ
December 2007 Page 61
Section 3 - Operation Loading/Unloading
3.10 Loading/Unloading
Know and heed all national, state/provincial and local
rules which apply to transporting of MEWPs.
Only qualied personnel shall operate MEWP during
loading/unloading.
Be sure vehicle capacity and loading equipment
hoists, chains, straps, etc., are sufcient to withstand
maximum MEWP weight shown on the serial plate on
the MEWP.
The transport vehicle must be parked on a level surface
and must be secured to prevent rolling while MEWP is
being loaded or unloaded.
3.10-1 Loading and Tie-down
1. Lock turret using turret transportation lock
(refer to Section 3.10-2).
2. Turn key switch to “ ” off position and remove
key before transporting.
3. Turn main power disconnect switch to “ ” off
position.
4. Chock MEWP wheels (if necessary).
5. Remove all loose items.
6. Anchor down MEWP to transport surface using
tie-down points (refer to Figure 3-2).
7. Secure boom from side-to-side movement using
lower platform mount between boom end and
platform. Do not use excessive downward force
when securing boom section.
WARNING
Inspect MEWP for loose or unsecured
items.
NOTE
For loading and unloading using a winch
line, refer to Section 2.5.
Figure 3-2. Tie-down Points