18_06_07_Battery Backup Distribution_10010371_ENG_V1.8 Seite -30- von -38-
Procedure
Carry out the procedure in accordance with the Original-SMA-System
documentation and paperwork!
After your successful system-commissioning and tightening of the cover
screw’s: Please attach the provided stick-on label alongside the Battery Backup
Distribution!
Place the label with the image for an "island mode system ability"(risk of
dangerous voltage applied even if the public grid is disconnected!); this label is
included in the scope of delivery. Please place it either on the domestic
junction box or at the counter/meter board.