12. Speedwire-connection Home Manager/Energy-Meter
Connect a suitable network-cable (our recommendation: type “Cat.5e” -or even better “Cat.7”-
is a very established twisted pair solution) to the network jack on the front of the SMA Home-
Manager respectively the SMA Energy-Meter.
Take the M25 cable gland with the included special sealing insert (sealing is divided for pushing
through the RJ45 connector) for installing the network-cable!
Pre-drilled blanks for inserting
the cable!
13. Initial Operation
Preconditions
Battery Backup Distribution is solidly mounted!
All the required cables are connected correctly!
PE-cabling to the main equipotential bus bar is done!
Perform all the electrical tests in accordance with your national standards! e.g.
insulation test, protective grounding test.
Document the test results for archiving in accordance with your national
standards!