SMA Solar Technology AG Commissioning
Installation Manual SB20HF-30HF-IA-IEN120431 57
7.3.4 Restarting the Self‑Test
In order to restart the self‑test, proceed as follows:
1. Disconnect the miniature circuit‑breaker and secure against re‑connection.
2. If a multi‑function relay is connected, switch off the multi‑function relay power supply.
3. Disconnect the Electronic Solar Switch from the inverter for 5 minutes and then connect it again.
4. Switch on the miniature circuit‑breaker again.
The inverter is now in the initialization phase and you can restart the self‑test, as described in
section 7.3.1"Starting the Self‑Test" (page52) from step 3.