9.3 Testing the Fans
You can verify the operation of the fans in two ways:
Set the parameter “Fan Test“ to "1" (with Sunny Data, Sunny Data Control or with the data
logger Sunny Boy Control).
or
Turn off the inverter by turning off all DC and AC disconnects and wait 5 minutes for any residual
voltages to dissipate.
Once the LED’s are off, remove the cover and set the jumpers as shown in the figure below.
Turn on the inverter by turning on the AC disconnect and then the DC disconnect or switch the
SMA DC-Disconnect to the "1" position.
Jumper Position for Fan Test
Jumper Position for verifiying the
operation of the fans