3 Initial Setup and Start SMA Solar Technology AG
32 SHP75-10-STP60-10-IA-xx-18 Installation Guide
Table 3.2 Display with control and function buttons
The screen design is divided into different sections:
1. Main screen. Current and daily yield.
This section contains:
Actual output power (kW)
Yield of the current day (kWh)
Total yield (kWh)
Current date.
Current time
Operating mode (#)
2. Inverter information. This section contains:
Inverter device type
Inverter name
Inverter serial number
IP address
Serial number of the SMA Inverter Manager
Software version of the inverter
3. Actual values This section contains:
PV voltage and current
Phase-to-phase voltages
Phase currents
Grid frequency
3.2.1 Initial Setup via LCS-Tool
The inverter and the SMA inverter manager must be
commissioned via the local commissioning and service tool
(LCS-Tool). Commissioning is necessary before the inverter
is connected to the AC utility grid and feed-in operation
begins.
The LCS too enables the selection of predefined country
data sets for different utility grids. Customer-specific country
data sets can be provided by SMA and imported via the
LCS-Tool (see installation manual of the SMA Inverter
Manager / SMA Digital I/O Box / LCS-Tool).
After installation, check all cables and close the inverter.
Turn on AC power.
3.2.2 Switching on the PV
Load-Break Switch
Figure 3.2. PV load-break switch
Switch on the PV load-break switch at the inverter and, if
available, at the PV array junction box.
3.2.3 Commissioning
The inverter starts automatically if sufficient solar irradiation
is available. Commissioning takes a few minutes. During this
period, the inverter performs a self-test.
On green LED
Alarm red LED
Button Function
Selecting the correct grid code is important in order to
comply with the local and national standards.
It is possible to create customer-specific grid code files
with adjusted set values (see Section 3.2.4).
INFORMATION
The inverter is protected against short-term reverse
polarity. The inverter does not generate feed-in
power until any reverse polarity is corrected.
Prolonged reverse polarity leads to a failure of the inverter
and thus will void the warranty.
Make sure that the cables are correctly connected to
the inverter.

Table of Contents