Figure 17: Synergy Manager with MC4 Connectors
To connect the DC wires to the Synergy Manager with DC wire lugs:
1.
Thread 12 - 20 mm diameter wires with a maximum of 50 mm
2
cross section through
the DC gland/.
2.
Route the DC wires to the DC+ and DC- terminals on the DC+ and DC- boards of the
Synergy Manager (see labels DC boards).
CAUTION!
The DC board has three pairs of DC terminals - each pair is connected to
single Synergy Unit (Left, Center and Right).
When installing a system with more than 3 strings per a single Synergy Unit
(whether connected directly or via a combiner box), fuses are required. In
SolarEdge system, 25A fuses must be used.
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
37 Connecting the PV Strings to the Synergy Manager