MECHANICAL INSTALLATION
HIGH TANK MODELS:
1. Put the pulper/extractor into position as shown on the Installation Drawings.
2. Place the Anti-Vibration Pads under each leg of the Pulper and Hydra-Extractor
®
. *
3. TRAY FEED UNITS ONLY - Install the tray to the Pulper (if it was not already installed
at the factory) using the provided gasket material and hardware.
4. TROUGH FEED UNITS ONLY - Install the provided trough gasket between the Pulpers
inlet and the trough outlet and secure with the provided hardware.
*