5 Mechanical Installation System Manual
22
Lifting device
Hook
U-hook
Connections
Notice
Insert the hook from inside
to outside.
Lateral pin of the U-hook should
be tightened.
National and local safety rules should be observed at all times.
Violating relevant safety rules may void pertinent warranty claims from Sungrow.
5.3 Foundation
5.3.1 Selection of Installation Site
When selecting the installation site, consider the following requirements at least:
Ambient and geological conditions, such as stress wave emissions, the level of
underground water table and etc. should be taken into account.
The ambient environment should be dry, well ventilated, and far away from
inflammable materials.
The ground at the installation site must be compacted enough. Relative compaction of
the ground should be equal to or greater than 98%. Otherwise, take proper methods to
strengthen the ground.
5.3.2 Foundation Requirements
Pay attention to the high weight of the MV Station. Check thoroughly the conditions on
the installation site (mainly the geographical and environmental conditions) before
designing and constructing the foundation.