2-1) INSTALLATION ENVIRONMENT
1) Temperature: ① 0~40℃ (32~104℉) when the machine is in operation
② -25~55℃ (-13~131℉) when the machine is not in operation
2) Humidity: 45~90% (relative)
3) Grounding: Ensure the electricity is properly grounded.
4) Close any doors and windows near the machine to prevent direct light, dust, and humidity.
5) Foundation under the machine must be a sufficiently strong and flat concrete to support the weight of the machine.
2-2) ELECTRICITY INSTALLATION
Check if the input voltage of the machine is in the right range of the voltage supply before installing or operating
the machine. The voltage required is as follows:
1) Input voltage (to be adjusted when installing): 100V, 110V, 120V, 200V, 220V, 240V
2) Allowed range of voltage: within 10% of the voltage set
3) Electric capacity and voltage consumption: 600VA 400W
4) Insulation resistance: over 10M ohms (measured with 500V insulation tester)
[CAUTION]
Do not let moisture drops on the machine.
Provide air conditioning to control humidity and to prevent dust and corrosion.
DANGER
WARNING
Properly ground the machine to avoid the possibility of electric shock. Use three-wire
grounding (grounding resistance below 100 ohms).
Check the voltage supply where the machine will be installed.
Install the cable away from the operator’s work space to prevent accident or injury.
MACHINE INSTALLATION AND ASSEMBLY
Install your machine in an appropriate environment and with adequate electrical supply. Failure to follow the
directions may result in machine malfunction.