Specification of excellent controller
Page - 10 -
Step 7: Confirmation for Wiring
Double-check the wiring in step1 through 5. Confirm correct polarity at
each connection. Verify that all 10 power terminals are tightened.
Step 8: Power-up sequence after confirmation of connection
1. Turn-on battery firstly !
2. Turn-on solar panel
3. Turn-on wind-turbine
4. Turn-on DC loading
5. Turn-on switch power for city-electric (if be this mode)
CAUTION
if you would take down system as need, must be comply with following
sequence.
1. Remove wind-turbine wiring firstly!