4-8 Parallel Operation
For this converter series, it is possible to operate models of the same type in parallel.
The maximum number of converters which can be operated in parallel is 10.
When using parallel operation, connect the PO terminal and ALM terminal of each converter to the same terminal of the
other.
As much as possible, insure that the width, length and material of the wiring used for connecting each converter to the load
are identical. There is the possibility that the current balance will collapse if there is a difference in the wiring from each
respective converter to the load.
DC
Input
+Vin
-Vin
+Vout
-Vout
PO
RC
ALM
Fuse SW
Load
+Vin
-Vin
+Vout
-Vout
PO
RC
ALM
Fuse
LED
Fig. 4-8 Example Parallel Operation Connection